How long does it take to build a granny flat?

Written by Clayton Bielby

Updated at April 5th, 2025

Contact Us

If you still have questions or prefer to get help directly from an agent, please submit a request.
We’ll get back to you as soon as possible.

Please fill out the contact form below and we will reply as soon as possible.

  • General
  • Product & Design
  • Installation & Delivery
  • Pricing & Payment
  • Compliance & Council Approvals
  • Warranty & Support
  • Optional Features & Upgrades
  • Process & Timeline
  • Sustainability & Efficiency
  • Design & Features
  • Installation & Site Preparation
  • Compliance & Regulations
  • Pricing & Financial Considerations
  • Septic & Wastewater Systems
  • Accessibility & NDIS Options
  • Expandify Knowledge Blogs
+ More

With Expandify, the process from contract to delivery generally takes 14–20 weeks, which includes:

Preliminary Stage (1–3 weeks): Prelim report, site data collection, and quoting

Contract & Manufacturing (8–9 weeks): Batch production offshore

Shipping & Delivery (6–7 weeks): Includes customs clearance and transport to site

Installation (0–4 weeks): Timing depends on builder availability and weather

Traditional site-built homes may take 4–6 months or longer. Expandify’s factory-controlled process allows faster delivery and reduced delays.

Was this article helpful?

Yes
No
Give feedback about this article

Related Articles

  • What is Expandify?
  • What makes Expandify different from traditional home builders?
  • What is an expandable modular home?
  • Are Expandify homes suitable as primary residences?
  • Where are Expandify homes manufactured?

Copyright 2025 – Expandify.

Knowledge Base Software powered by Helpjuice

Expand