What is the average lead time from deposit to handover?

Written by Clayton Bielby

Updated at March 31st, 2025

Contact Us

If you still have questions or prefer to get help directly from an agent, please submit a request.
We’ll get back to you as soon as possible.

Please fill out the contact form below and we will reply as soon as possible.

  • General
  • Product & Design
  • Installation & Delivery
  • Pricing & Payment
  • Compliance & Council Approvals
  • Warranty & Support
  • Optional Features & Upgrades
  • Process & Timeline
  • Sustainability & Efficiency
  • Design & Features
  • Installation & Site Preparation
  • Compliance & Regulations
  • Pricing & Financial Considerations
  • Septic & Wastewater Systems
  • Accessibility & NDIS Options
  • Expandify Knowledge Blogs
+ More

Answer:
The typical lead time from signed contract and deposit to handover is 18 to 24 weeks, depending on your build type and approval pathway.

Timeframe overview:

  • Prelim stage & approvals: 3–6 weeks
  • Selections and contract finalisation: 1–2 weeks
  • Batch manufacturing: 8–10 weeks
  • Shipping & delivery: 5–6 weeks
  • Installation & handover: 1–3 weeks

Timeframes can vary based on:

  • Council processing speed (CDC vs DA)
  • Access or transport complexity
  • Custom upgrades or material delays
  • Regional delivery or extended site works
  • Where you are based in the batch for installation on site. After delivery to site there can be a waiting period for the building team to arrive and install. You will be updated on the estimated date for both delivery and then install.

Your assigned sales and project manager will provide timeline updates at every stage to ensure clarity and confidence.


 

 

 

 

 

 

 

 

 

 

 

 

 

 

transfer period delivery time

Was this article helpful?

Yes
No
Give feedback about this article

Related Articles

  • What are the steps to purchasing an Expandify home?
  • What is the Batch Production Process, and how does it work?
  • How long does it take to manufacture an Expandify home?
  • How long does shipping take once my home is ready?
  • What happens during the handover process?

Copyright 2025 – Expandify.

Knowledge Base Software powered by Helpjuice

Expand